PowerLoad recently delivered 1MW of liquid load testing for a global colocation provider in Sweden, validating liquid cooling performance at every rack position and proving the infrastructure under real operating conditions.
We've just finished commissioning liquid cooling in Sweden for a global colocation provider: air cooled racks converted to high density liquid cooling, with Level 4 and Level 5 testing at every rack position.

We supplied 2 x 500kW liquid load banks, 2 commissioning manifold trolleys and a custom built PDU. Each load bank fed a manifold trolley serving up to 8 rack positions, with pressure drops balanced at every position to prove the CDUs under real operating conditions. The site had a power limitation, so the PDU provided the 2 x 800A supplies the load banks needed.

The testing covered the CDUs, chiller performance, the primary and secondary cooling networks and full IT load simulation, and showed where individual rack positions could be optimised.

Our scope was setup and demobilisation. The team stayed on site for the whole testing programme anyway, evenings and weekends included, to keep it on track.